Run a Project Analysis
The Acumen Fuse analysis engine uses a combination of ribbons and metrics to run project analytics.
These steps assume that you have already imported a project into Acumen.
To run a project analysis, complete the following steps:
- Select the S2 // Diagnostics tab.
- Select a pre-defined analysis view using the tabs at the bottom of the screen.
- In the Analyze group click Fuse to run the analysis.
- Click on any metric result, ribbon, or phase to view the included activities in the Activity Browser.