Run an Automatic Activity Goal-Based Acceleration
Use automatic goal-based acceleration to define the acceleration target and let Acumen 360 automatically generate the schedule scenario that meets that goal.
To define an acceleration goal for a specific activity, complete the following steps:
- Select the S4 // Acceleration tab.
- In the Acceleration group, click Accelerate Schedule.
-
On the Accelerate Schedule dialog box, in the Schedule Accelerator group:
- Select the Accelerate Activity tab.
- Click Select / Change Activity to Accelerate to select the activity against which the acceleration needs to be conducted (for example, accelerate completion of construction).
- Use the goal options (date field or sliding scale) to set the target goal for the activity acceleration.
- Click OK to run the simulation.
- Compare the results using forensics, timeline, and analysis views.