Set the Uncertainty Loading Level
Setting the risk loading level is a means of making the risk loading process practical, avoiding the need to manually risk load every single activity within your potentially large schedule.
To set the uncertainty loading level, complete the following steps:
- Select the S3 // Risk tab.
- In the Activities group, click the Activity View down-arrow then hover over Grouping to display a sub-menu where you can adjust the Display Level slider.
- Set the level based on the level at which you want to risk load your risk model.