Activity View Procedures
Use these procedures when working with the Activity view.
Related Topics:
- Add Columns
You can add columns such as Activity Count and WBS Code to the Activity view. - Add the Activity Type Ex Column
Add the Activity Type EX column to the view so that you can see if a milestone is a start or finish milestone. - Change an Activity Work Breakdown Structure
Before you change the work breakdown structure of an activity, you must group by WBS. - Change Time Now and Update Progress
Change Time Now for a project and specify whether you want to automatically progress work as planned or reschedule uncompleted work to start after Time Now. - Expand or Collapse Activity Groupings
Activities must be grouped in order to use the expand or collapse feature. - Expand or Collapse the Entire Project
Use the Display Level slider to expand or collapse the entire project. - Group Activities
Group activities by WBS, activity, user-defined fields, or code fields. - Remove Columns
Remove columns from the S1 // Projects tab Activity view. - Set the Display Units
Set the duration and work data display units. - Ungroup Activities
Use the Flat option to ungroup all activities.
Parent Topic: S1 // Projects Tab Procedures
Related Concepts