Manually Map an Activity to Multiple Risks
You must map risk events to activities/cost elements in order to include them in the risk model. Use these steps to manually map an activity to multiple risks.
To manually map an activity to multiple risks, complete the following steps:
- Select the S3 // Risk tab.
-
On the Views group, click:
- .
- .
- In Activities (left pane), select the activity that you want to map.
- In the Risk Register (right pane) Mapped column, select the check box next to the risks you wish to map to the selected activity. After mapping has been applied, you have the option to override the mapped impacts using the Risk Events tab beneath the activities (left pane).
- Optional. In the Risk Register (right pane) Absolute Mapping column, select the check box next to the risk(s) for which you want to use absolute mapping.