Edit a Resource Assignment

Use the Resource tab of the Change Details form to edit the resource assignments of an activity.

For more information, see Activities Overview and Change Details Overview.

This topic covers two different procedures. Select the steps you need based on the Workflow Type Configuration setting:

Before you begin, review Rules for Editing Change Details Data.

When the "Model Change as" Option is Set to "A New or Change Amount"

If the Workflow Type Configuration Model Change as option is set to A New or Change Amount, you will be unable to edit existing resource assignments. To delete a resource assignment or to reduce hours, you must insert a new line and enter a negative value to indicate a change. To increase hours, you must insert a new line and enter a positive value to indicate a change. Upon final approval of the change request, the difference between the two values is rolled into the final budget.

For example, if a painter has 800 hours assigned and you want to reduce the hours to 600, you must insert a new line and add a painter resource assignment with an amount of -200 hours. Upon final approval, the painter resource assignment will have 600 hours rolled into the budget.

To edit an existing resource assignment when the A New or Change Amount option is selected:

  1. On the Navigation menu, click Workflows » Change Management.

  2. In the List View, select the Change Request.

  3. On the General tab of the Change Request Form, click the Change Details button.

    The Change Details view and barchart displays.

  4. Select the activity that is associated with the resource assignment you want to edit.

  5. Click the Resources tab, and take one of the following actions:

  6. Click Save.

When the "Model Change as" Option is Set to "A Replacement of Existing Time Phased Data"

If the Workflow Type Configuration Model Change as option is set to A Replacement of Existing Time Phased Data, you will be able to edit existing resource assignments.

To edit an existing resource assignment when the A Replacement of Existing Time Phased Data option is selected:

  1. On the Navigation menu, click Workflows » Change Manage.

  2. In the List View, select the Change Request.

  3. On the General tab of the Change Request Form, click the Change Details button.

    The Change Details view and barchart displays.

  4. Select the activity that is associated with the resource assignment you want to edit.

  5. Click the Resources tab.

  6. In the Resources grid, select the resource assignment you want to edit, and edit the information as needed.

  7. Click Save.

What do you want to do?

Delete a resource assignment

Insert an activity to a work package

Delay the start of an activity

Select the Create, Edit, or Delete Activities option

Change the EVT for an activity

Add a predecessor or successor relationship to define when an activity occurs

Add a relationship to an activity

Add a resource to an activity

Add time phased data


Learn more about...