Update Baseline Dialog Box

Use the Update Baseline dialog box to update an existing baseline, if you have rights to do so.

Open Plan creates an opwin.log session log each time you perform baseline processing. This logs all options on the Update Baseline and Add Baseline dialog boxes.

After a baseline has been created, you can update it with the current Project Properties at any time. When updating an existing baseline, you can have Open Plan update information for activities already present in the baseline as well as for new activities (that is, activities missing from the original baseline).