Multiple Baselines Dialog Box

Use the Multiple Baselines dialog box to select up to three baselines for reporting purposes. You can change these selections at any time.

Each Baseline field displays the list of currently defined baselines for the project from which you can select.

While you can specify the Project Management Baseline (PMB), if it exists, as one of the three baselines, Open Plan uses the PMB for cost calculations even if it is not among those selected on this dialog box.

If there is no baseline named PMB, Open Plan uses the baseline selected as Baseline 1 for cost calculations.