Update a Baseline

Use this procedure to update a baseline.

To update a baseline:

  1. In the Project Views folder of Open Plan Explorer, display a project in any view.
  2. On the Processes tab, select Baselines from the Dialogs menu group.
  3. In the Baselines dialog box, select the baseline you want to update and then click Update.
    If you have not selected the baseline previously for the selected project, Open Plan will ask you if you want to select it. Click Yes.
  4. Use the Update Baseline dialog box to make the necessary changes to the baseline.
  5. Click OK.

You can also display the Baselines dialog box by clicking Select Baseline on the Summary tab of the Project Properties dialog box.