Create a New Baseline
Use this procedure to create a baseline.
To create a baseline:
- In the Project Views folder of Open Plan Explorer, display a project in any view.
- On the Processes tab, select Baselines from the Dialogs menu group.
- In the Baselines dialog box, click New.
- In the Add Baseline dialog box, enter a name and a description for the baseline.
- From the Based On list, select whether you want to use Early, Late, or Scheduled dates for storing information related to resources and costs.
- Click the appropriate options for progressed activities.
- Click OK.
You can also display the Baselines dialog box by clicking Select Baseline on the Summary tab of the Project Properties dialog box.