Select a Baseline

Use this procedure to select a baseline.

To select a baseline:

  1. In the Project Views folder of Open Plan Explorer, display a project in any view.
  2. On the Processes tab, select Baselines from the Dialogs menu group.
  3. In the Baselines dialog box, select a baseline and then click Select.
    If you do not want to load a baseline with the project at this time, select <No Baseline> from the list. You can also select the Clear baseline data when No Baseline is selected option to clear activity baseline data. This option is enabled only when you selected <No Baseline>.

    If you select <Multiple Baselines>, the Multiple Baselines dialog box displays, which enables you to select up to three baselines for reporting purposes.

    Attention: For more information, see Select Multiple Current Baselines.

    You can also display the Baselines dialog box by clicking Select Baseline on the Summary tab of the Project Properties dialog box.