Use this procedure to select a baseline.
-
In the
Project Views folder of Open Plan Explorer, display a project in any view.
-
On the Processes tab, select
Baselines from the
Dialogs menu group.
-
In the Baselines dialog box, select a baseline and then click
Select.
If you do not want to load a baseline with the project at this time, select
<No Baseline> from the list. You can also select the
Clear baseline data when No Baseline is selected option to clear activity baseline data. This option is enabled only when you selected
<No Baseline>.
If you select
<Multiple Baselines>, the Multiple Baselines dialog box displays, which enables you to select up to three baselines for reporting purposes.
You can also display the Baselines dialog box by clicking
Select Baseline on the Summary tab of the Project Properties dialog box.
Related Topics
Related Procedures