Options Tab

Use the Options tab to control how risk analysis is performed.

Note: For key activities, Open Plan provides a cumulative distribution for each calculated date and float. This information is output to the Risk table. By default, values are provided for 21 percentile points (0, 5, 10… 100). In addition to these fields, you can also use the RiskPercentileArraySize field in the Options dialog box Advanced tab to control the granularity by specifying the number of intervals (which will be evenly spaced).