Risk Tab
This tab allows you to specify the probability distribution information about the duration of an activity. This information is used in risk analysis calculations.
For example, assume that you suspect an activity will take 10 days, but you want to allow for an uncertainty of plus or minus 2 days. You would define the probable range of durations with the following values:
| Field | Value |
|---|---|
| Optimistic | 8 days |
| Pessimistic | 12 days |
| Most likely | 10 days |
While you could assign any shape to the probability distribution, you would most likely assign it the Normal distribution.
You cannot enter probability information for any type of activity that uses a calculated duration – subprojects, external subprojects, and hammocks.
Contents
| Field | Description |
|---|---|
| ID, Desc., Status, Duration |
These fields are common to all tabs. See Common Fields for a description of these fields. |
Duration
Open Plan provides controls for defining the probable range of durations for the activity.
| Field | Description | ||||||||
|---|---|---|---|---|---|---|---|---|---|
| Shape |
This field allows you to select the shape of the probability distribution as follows:
In addition, you can select None if you do not want to assign a probability distribution shape. |
||||||||
| Optimistic |
This is the minimum estimated duration for the activity. |
||||||||
| Pessimistic |
This is the maximum estimated duration for the activity. |
||||||||
| Key Activity |
This field allows you to designate the activity as a key activity. For key activities, the program stores the most detailed risk analysis information possible. To avoid creating an unmanageably large output file when risk analysis is performed, keep the number of key activities to a minimum. It is recommended that you flag no more than a dozen or so key activities per project. |
||||||||
| Probability of Occurrence |
Enter a value from 0 to 100 as a weight factor to indicate the probability that the activity exists at all. For example, assume you have the following three activities:
Activities A and B will always happen, but we might judge that there is only a 20% chance that following testing, we have to go back and fix the software. All regular Open Plan features ignore this field (and always consider all tasks) except Risk Analysis, which would only consider activity C 20% of the time. If Risk Analysis chooses to ignore the task on any given iteration, then any successors of C are deemed to follow immediately on from B (as if C had zero duration). |