Tabs and Dialog Boxes
- Related Topics:
- Activity Details Dialog Box
- Activity Information Dialog Box
- Activity Tree Dialog Box
The Select Activity dialog box allows you to change the target activity without having to exit the tool, select a new activity, and re-run the tool. - Add Relationships Dialog Box
Use the Add Relationships dialog box to define logical predecessor and successor activities. - Add Relationship Dialog Box
Relationship information defines the logical relationship between activities in your project. - Assign Multiple Resources to Multiple Activities Dialog Box
This dialog box allows you to assign multiple resources to any number of activities at one time. - Delete Activity Dialog Box
When you delete a single activity from a project, you can use this dialog box to instruct Open Plan to take one of the following actions: - Dictionaries Dialog Box
The Dictionaries dialog box enables you to open and close user dictionaries and to edit the contents of an open user dictionary. - Edit Relationship Dialog Box
Use this dialog box to edit a relationship between activities. It defines the relationships between activities using the following settings: - Find Code Dialog Box
This dialog box features an input box and options that you can use to specify the manner in which Open Plan should conduct a search for the code. - Link/Unlink Activities Dialog Box
Use this dialog box to add and remove multiple relationships of the same type between activities conveniently. - Move Activities Dialog Box
Use this dialog box to move activities from one external subproject to another, or from an external project to a master project. - Open External Subprojects Dialog Box
When you open a project containing external subprojects, Open Plan displays the Open External Subprojects dialog box, which contains a hierarchical list of external subprojects (and externals embedded within the top layer of externals). - Output Fields Dialog Box
Use the Output Fields dialog box to customize the columns that you want to display either on the Path Details or Summary Path report. - Redundant Logic Dialog Box
After running redundancy analysis, use this dialog box to view and delete the redundant relationship. - Replan Activity Dialog Box
Use this dialog box to set options for replanning an activity. - Select Code Dialog Box
This dialog box works with the values on the Codes tab of Activity Details dialog box and Project Properties dialog box. - Spread Method Dialog Box
This dialog box displays a list of spread curves that you can use to respread the total quantity of the selected resource over the activity’s original duration.
Parent Topic: Working with Activities