Risk Analysis
- Related Topics:
- Risk Analysis
Project management decisions are concerned with the future. While planners hope to influence the outcome of events by the decisions they make, everything about the future is, to a greater or lesser extent, uncertain. - Defining Activity Risk
To use the risk analysis feature in Open Plan, you must enter duration probability information for at least one activity in a project. More typically, you enter probable durations for all activities that involve at least some degree of uncertainty in their planning. - Risk Analysis Operations
You can perform a risk analysis of a project at any time. In many ways, the risk analysis function in Open Plan is similar to the time analysis process. - Interpreting the Results of Risk Analysis
Open Plan provides a number of views that you can use to display the results of risk analysis. - The Effect of Risk Analysis on Start Dates
In general, the early start dates calculated by risk analysis will be later than those in a project using standard time analysis. - How Risk Analysis Calculates Finish Dates
Open Plan does not generate the mean and standard deviation values of the finish dates for each activity directly during risk analysis. - How Risk Analysis Interprets Durations
In general, risk analysis interprets the value in the Original Duration field as the mode (most likely) value. - Probability in Durations
With Open Plan, you can estimate the durations of any uncertain activities by using different types of information to create a probability distribution. - Progress and Duration Probability
By conducting risk analysis on projects that have already recorded progress, you can accurately gauge the reliability of the remainder of the project schedule. - Combining Probabilities
In addition to enabling us to analyze a single process, probability theory also provides the analytical tools to combine probability distributions in ways appropriate to specific circumstances. - Risk Analysis Output Files
The results of an Open Plan risk analysis are potentially extensive, requiring some method to summarize this information for later use. - Risk Histograms
A risk histogram view presents the detailed picture of the probability distribution for calculated dates for a key activity. - The Concept of Sampling Error
Because the mean and standard deviation of a probability distribution are based on the sampling of Monte Carlo simulations, they are only estimates and, therefore, have a possible error. - Monte Carlo Simulation Technique
If we could perform a process a large number of times, we could build up a histogram to represent the probability distribution from the individual outcomes of each trial. - Probability Some Background Information
- Tabs and Dialog Boxes
- Related Procedures
Parent Topic: Project Analysis