BCR Analysis Report Overview

The purpose of the BCR Analysis report is to confirm that the change request data has been correctly added to Cobra and Open Plan as well as providing summary and detailed information about the changes processed in a particular period. The report displays before and after data for change requests processed for a period and highlights any discrepancies; that is, data that did not get processed as planned.  

You can access the report from the Reports menu on the Navigation tab if the snapshot database has been configured in Cobra.

The report displays workflow types that meet the following criteria:

You can use the report options fields to customize the report. You can filter the data in the report by project, control account, CAM, change number, and/or stage. If you want to include the report on a dashboard, you can save the report and create a Files dashpart.

After you enter your selection criteria in the Reports » BCR Analysis view and click Run Report, PM Compass generates the report as an Excel spreadsheet, saves it to the Links folder (specified in Administration » System Settings » File Folders), and sends you an email with a hyperlink to the report. The report filename is BCR Analysis_<user ID>_<Date/Timestamp>. You can click the View Status button to make sure the job is picked up by the process server and see the status of the job running.

The report includes the following tabs:

When you run the report, select the Only Include Workflows that Contain Discrepancies option to filter the report by displaying only the workflows with information highlighted in red in the After section.

If the time-phasing of the costs between the Requested section and the After section do not match, the values are highlighted. A common scenario that will cause highlighting of the time-phased values is when the status date on the workflow form during the time the workflow was in approval did not match the status date of the live project at the time the workflow was completed. In order not to change history in the live project, the status date on the workflow form is updated to match the status date of the live project. For more information, see BCR Analysis Report is Highlighting Dates/Values as Discrepancies but there are No Errors.

For information about how time-phased data displays in the report, see Time Phased Data in the BCR Analysis Report.

BCR Analysis Snapshots

A snapshot is a picture of the data at a certain point in time. PM Compass creates snapshots of data from the change request and the live project. The BCR Analysis report is generated from these snapshots. This allows the report to display what was in the project before the workflow was completed, and what was in the live project just after the workflow completed. For more information, see BCR Analysis Snapshots.

In order to use this report, you must set up a snapshot database in Cobra and have workflows that have been created since the snapshot database was created. Refer to "Appendix K: Managing BCR Snapshot Database" of the Cobra Installation Guide for details about how to create a snapshot database and how to link the snapshot database in the Cobra Data Tool.

The Reports menu in the Navigation bar will not display BCR Analysis if the snapshot database is not configured.

Things to Note

What do you want to do?

Set report options


Learn more about...

View location