BCR Analysis Snapshots

A snapshot is a picture of the data at a certain point in time. PM Compass uses a combination of the snapshot data, the data in the change request, and the current data to produce the BCR Analysis report.

Snapshots are only created when the workflow type uses a budget class for the change class. You can see these settings on the Change Details on Form tab in Workflow Type Configuration. The snapshot database resource file and calendar file come from the project specified in the Workflow Type Template Project field on the Change Details on Form tab.

If you cancel a workflow, the system deletes the associated snapshots.

Snapshot Database

In order for PM Compass to produce a BCR Analysis report, you need to create a snapshot database. See "Appendix K: Managing BCR Snapshot Database" of the Cobra Installation Guide for steps to configure the BCR Snapshot database.

During the snapshot database setup, make sure that you log in to the Cobra Data Tool as an Administrator. If you don't run it as Administrator, you will still get the green check letting you know that everything was completed successfully but when you log into Cobra, you will not see the connection that you just added.

Types of Snapshots

The following snapshots are created for the BCR Analysis report:

This is helpful when you have multiple workflows with the same control account. For example, if you have two workflows with the same control account, when you complete the first one, the budgeted hours change because the data is updated with the change request. When you complete the second workflow, the Before Snapshot includes the updated budgeted values from the first workflow.