Reported Percent Complete inquiry
You enter Reported Percent Complete (RPC) on the Manage tab of the Project Command Center to indicate the amount of a project or phase that is complete on a specific date in the project lifecycle. You use RPC to track the progress of your projects.
Use this inquiry to see the percentage of work on a project completed by a specified date.
If needed, you can add predefined columns and view supplemental information such as project/phase status and resource key.
Using the inquiry
From the > Reports menu, click Standard Inquiries > Project > Reported Percent Complete.
Audience
Accounting staff
Standard columns
Column | Links to this inquiry | Description | Date range available |
---|---|---|---|
Project/Phase ID & Description |
Phase |
The project and phase IDs and descriptions associated with the reported percent complete |
|
Date Entered |
The date the reported percent complete was entered on the Manage tab of the Project Command Center |
||
Percent |
The percent complete reported on the Manage tab of the Project Command Center |
Predefined columns
You can add predefined columns to this inquiry.
Column | Links to this inquiry | Description | Date range available |
---|---|---|---|
Reported Percent Key |
The database identifier of the reported percent complete |
||
Project Key |
Project |
The database identifier of the project associated with the reported percent complete |
|
Project ID |
Project |
The ID of the project associated with the reported percent complete |
|
Project Description |
Project |
The description of the project associated with the reported percent complete |
|
Project ID & Description |
Project |
The ID and description of the project associated with the reported percent complete |
|
Project/Phase Key |
Phase |
The database identifier of the project/phase associated with the reported percent complete |
|
Project/Phase ID |
Phase |
The ID of the project/phase associated with the reported percent complete |
|
Project/Phase Description |
Phase |
The description of the project/phase associated with the reported percent complete |
|
Project/Phase Status |
Phase |
The status of the project/phase associated with the reported percent complete Examples: Active, Inactive |
|
Order |
The position of the reported percent complete on the Manage tab in the Project Command Center Example: You may sort the inquiry by RPC order so it mirrors the order of the tasks on the Manage tab. |
||
Resource Key |
Resource/Task |
The database identifier of the resource associated with the reported percent complete |