Supply Subtask
Use this subtask to view details about the supplies that make up the supply quantity in the selected row of the main screen.
Supply items displayed are those with a need date later than the end date of the previous time bucket row and earlier than or the same as the period end date of the current time bucket. Results are sorted by Planned Available Date and Supply Type.
Use this subtask to view details on the various supplies that make up the total supply quantity for the time bucket selected on the main screen.
Contents
Field | Description |
---|---|
Part |
This field displays the part ID shown on the main screen. |
Rev |
This field displays the revision of the part ID. |
Description |
This field displays the description for the part ID. |
U/M |
This field displays the unit of measure assigned to the part ID. |
Selection Criteria
This group box display information as specified in the main screen.
Field | Description |
---|---|
Selection Option |
This field displays the project grouping option that defines which inventory projects are to be displayed.
|
Include Common Inventory |
This field displays Y (Yes) if the Include Common Inventory check box is selected in the main screen. Otherwise, this field displays N (No). |
Warehouse |
This field displays the warehouse for this supply/demand information. |
Project |
This field displays the inventory project for the supply information. The adjacent unlabeled field displays the description for this project ID. |
Proj Abbrev |
This field displays the abbreviation for the selected project ID. |
Netting Group |
This field displays the inventory netting group for supply information. The adjacent unlabeled field displays the description for this netting group. |
Period Start Date |
This field displays the starting date of the period for which supply information is displayed. |
Period End Date |
This field displays the ending date of the period for which supply information is displayed. |
Supply Information
This table window displays the supply information for the indicated Selection Criteria.
Field | Description |
---|---|
Planned Available Date |
This field displays the date on which the order will become available, including MO lead times for stocking or PO lead times for receiving and inspection. |
Due Date |
This field displays the date on which the supply is due from the vendor (for a purchased part) or from the shop (for a manufactured part). |
Supply Quantity |
This field displays the supply quantity for the line. |
Supply Yield Quantity |
This field displays the supply quantity adjusted for the part's yield factor. This field is displayed if you selected the Incl Scrap/Yield % in Planning Process check box on the Configure Production Control Settings screen in Costpoint Production Control. |
Supply Type |
This field displays the type of supply for the row. The types include:
|
Order/Requisition |
This field displays the order or reservation number referenced on the row. |
Release |
This field displays the release number of the order or reservation ID referenced on the row. |
Line |
This field displays the line number of the order or reservation referenced on the row. |
Status |
This field displays the status of the order or reservation referenced on the row. |
Project |
This field displays the project ID corresponding to the order or reservation referenced on the row. |
Project Name |
This field displays the name of the project corresponding to the project ID referenced on the row. |
Project Abbrev |
This field displays the project abbreviation corresponding to the project ID referenced on the row. |
Inventory Abbrev |
This field displays the inventory abbreviation associated with the order or reservation referenced on the row |
Inventory Abbrev Name |
This field displays the inventory name for this Inventory Abbrev. |
DPAS Priority |
This field displays the Defense Priority Acquisition System (DPAS) priority code for the project associated with the supply row. |
Delivery Schedule Exists |
If selected, this check box indicates that there are multiple delivery schedules that exist for the PO line. This check box is cleared and disabled for new lines. |
Subtasks
Subtask | Description |
---|---|
Purchase Order Supply | Click this link to open the Purchase Order Supply subtask and view details of the purchase order for the selected supply information. |
Requisition Supply | Click this link to open the Requisition Supply subtask and view details about the requisitions line for the selected supply information. |
Manufacturing Order Supply | Click this link to open the Manufacturing Order Supply subtask and view details of manufacturing orders for the selected supply information. |
Reservation Supply | Click this link to open the Reservation Supply subtask and view details of the supply reservation made for the selected supply information. |
Planned Order Supply | Click this link to open the Planned Order Supply subtask and view details about the MRP-generated planned order supply for the selected supply information. |
- Related Topics:
- Purchase Order Supply Subtask
Use this subtask to view details of the purchase order for the selected row on the Supply subtask. - Requisition Supply Subtask
Use this subtask to view details about the requisitions line for the selected row on the Supply subtask. - Manufacturing Order Supply Subtask
Use this subtask to view details of manufacturing orders for the selected row on the Supply subtask. - Reservation Supply Subtask
Use this subtask to view details of the supply reservation made for the part in the selected row on the Supply subtask. - Planned Order Supply Subtask
Use this subtask to view details about the MRP-generated planned order supply selected on the Supply subtask.