Purchase Order Supply Subtask
Use this subtask to view details of the purchase order for the selected row on the Supply subtask.
This subtask displays the information on the PO line, the PO Header, and the associated expedite notes. Use it to view further details about the PO supply on the Supply subtask.
Contents
Field | Description |
---|---|
Part |
This field displays the part ID shown on the main screen. |
Rev |
This field displays the revision of the part ID. |
Description |
This field displays the description for the part ID. |
U/M |
This field displays the unit of measure assigned to the part ID. |
Purchase Order |
This field displays the purchase order ID. |
Release |
This field displays the release number of the purchase order. It is 0 for standard POs. Blanket POs can have various release numbers. |
Line |
This field displays the line number of this line within the purchase order. |
Vendor |
This field displays the name of the vendor to whom this PO has been issued. The vendor name and address are displayed in the adjacent unlabeled fields. |
Status |
This field displays the status of the PO line. Only PO lines with a status of Pending or Open are included. |
Buyer |
This field displays the buyer assigned to the PO. |
Change Order |
This field displays the change order number of the PO. |
Warehouse |
This field displays the ID of the warehouse associated with the purchase order. |
Planner |
This field displays the ID of the planner assigned to the PO line. |
Inv Abbrev |
This field displays the inventory abbreviation for which this inventory part has been ordered. The name of the inventory abbreviation is displayed in the adjacent unlabeled field. |
DPAS |
This field displays the Defense Priority Acquisition System (DPAS) priority code for the project associated with the inventory abbreviation on the PO line. |
Project |
This field displays the project ID associated with the inventory abbreviation on the line. The project name is displayed on the adjacent unlabeled field. |
Prj Abbrev |
This field displays the abbreviation of the project ID. |
Plnd Avail Date |
This field displays the date on which the part should be available after allowing for purchase, receiving, and inspection lead times. |
Due Date |
This field displays the date on which the PO line is due for delivery. |
Desired Date |
This field displays the date on which the part on the PO line is desired by the requester. |
Order Qty |
This field displays the quantity order on the PO line in the inventory unit of measure. |
Open Qty |
This field displays the quantity on the PO line (in the inventory unit of measure) that has still not been fulfilled. |
Yield Qty |
This field displays the Open Qty with yield/scrap percentages factored in. This field is displayed if you selected the Incl Scrap/Yield % in Planning Process check box in the Configure Production Control Settings screen in Costpoint Production Control. |
PO Expediting Notes |
This text box displays expediting notes related to the PO. |
PO Line Expediting Notes |
This text box displays expediting notes related to the PO line |
Delivery Schedule Exists |
If selected, this check box indicates that there are multiple delivery schedules that exist for the PO line. This check box is cleared and disabled for new lines. |
Subtask
Subtask | Description |
---|---|
Delivery Schedule | Click this link to open the Delivery Schedule subtask and view details of the delivery schedule of the purchase order for the selected supply information. |
- Related Topics:
- Delivery Schedule Subtask of Purchase Order Supply
Use this subtask to view the multiple delivery schedule of a purchase order (PO).