Advanced Tab

Use the Advanced tab to set the Multiple Ends and Out of Sequence time analysis processing options.

You can also perform time analysis in Batch Mode. This enables you to run time analysis for multiple projects at one time. To run time analysis in Batch Mode, select more than one project from the Details pane of the Open Plan Explorer, and click the Time Analysis button. The Time Analysis [Batch Mode] dialog box will display. Set your options and then click OK.

If a project is closed, Open Plan will open it in Exclusive mode, perform the process, save the changes, and then close the project. If a project cannot be opened in Exclusive mode (because another user has it open in Exclusive or Shared mode), it will be skipped.

If you have a project open when the batch process is run, time analysis will be performed on the project, but the changes will not be saved and the project will remain open. You must manually save the changes yourself.

Open Plan creates one time analysis session log, listing the project results in the order in which the projects were processed in the batch.

Related Topics

Related Procedures