When to Perform Time Analysis

If you have selected the option to perform time analysis whenever data changes, you do not need to specifically perform time analysis, as Open Plan performs this calculation automatically.

If you have not selected the automatic time analysis feature, you can perform time analysis at any time. Typically, you will want to perform this calculation when you have:

  • Entered all the activities for a project
  • Changed the logic of the project, for example:
    • You have added or deleted one or more activities and their relationships.
    • You have changed the target dates or durations of one or more activities.
    • You have changed the relationship between any two activities.
  • Changed the calendars used by the project
  • Changed Time Now
  • Entered progress information for any activities in the project
  • Changed the target start or finish date for the project