If you are the Approver for a progress entry, you can either approve or reject the changes made by the Assignee to the cost progress entry.
To approve schedule progress:
On the Navigation menu, click Projects ยป Projects.
On the Projects form, select a schedule project.
On the Projects Form toolbar, click Approve Progress.
Select the progress entries that you want to approve by marking their corresponding check boxes in the Select column.
To view the changes performed by the Assignee on a progress entry, click under the Delta () column for the progress entry.
To view the work package to which an schedule activity rolls into in the Cost Analysis view, click the work package link in the Work Package field in the Cost Links group box of the General tab. For more information, see View the Work Package Linked to an Activity in the Cost Analysis view.
Click Approve on the Approve Schedule Progress Form toolbar. The status under the Workflow Status column changes to Approved.
Approve progress for a workflow that is not assigned to you
View changes made to a progress entry
View resources assigned to an activity
View the work package linked to an activity in the Cost Analysis view
Find activities that are not progressing according to plan
Learn about setting up approvers and assignees