The schedule process that creates the progress entries runs by project. PM Compass checks each project to see if the source system to update on the Progress tab of the Projects Form View is schedule or cost.
For more information, see Progress Overview.
If the project option indicates that progress is entered through the schedule, PM Compass creates new progress entries using the following conditions:
Activities that are in progress (the activity has an actual start date but not an actual finish date) OR
Have a forecast start before the end of the next period (Progress cycle end date + Progress cycle frequency)
Where “forecast start” is defined using the Schedule Forecast Date Set option on the Progress tab of the Projects Form View.
The valid options are:
Early
Late
Scheduled
If the project option indicates that progress is entered through into the cost system, PM Compass creates new progress entries using the following conditions:
Work Package EVT is not planning package AND
Work Package is in progress (flag =’O’) OR the forecast start for the Work Package is before or equal to the end of the next period date.
As each progress entry is created, the assignee and approver are determined using the Assignment Mapping grid on the Progress tab of the System Settings form.