Use the Enter Cost Progress form or Enter Schedule Progress form to view the changes made to a progress entry.
If you are the Approver, you can view the changes made to a progress entry from the Approve Cost Progress form and Approve Schedule Progress form.
To view progress history from the Enter Cost Progress form or Enter Schedule Progress form:
Enter the cost progress or schedule progress. For more information, see Enter Cost Progress or Enter Schedule Progress.
In the "Delta" column, click for the progress entry for which you want to see progress history.
The Progress Changes dialog box displays the old and new values of the fields that you updated for the selected control account/work package or activity, depending on whether you are updating cost progress or schedule progress.
Enter progress for a progress entry that is not displayed
Find control accounts or work packages that are not progressing according to plan
View explanation of variance for a control account or work package
View time phased resource data for a control account or work package