Use the Change Details view to delete a work package (WP). You cannot delete a work package that is already completed. If you delete a work package, all activities under that work package will also be deleted.
To delete a work package, complete the following steps:
On the Navigation menu, click Workflows » Change Management » select a Change Request.
In the List View, select the Change Request.
On the General tab of the Change Request Form, click the Change Details button. The Change Details view and barchart displays.
Select the work package from the grid.
On the Change Details grid toolbar, click Delete.
Click Save.
Delay the start of an activity
Add a predecessor or successor activity to define when an activity occurs
Add a relationship to an activity
Assign a resource to an activity