In the Change Details view, there are a number of rules that dictate when you can edit data. In general, you can edit a control account, work package, or activity if it is in-progress, but not if it is complete. If you have activities below a work package, the activities drive the work package dates so they cannot be edited manually. Similarly, if you have resource assignments on an activity, you cannot manually add costs to the work package. These rules enforce the cost/schedule integration.
This topic includes rules for working with:
Rules for Working With: |
Description |
The Change Details view is designed to allow CAMs to edit only their own work. For example, if a Contract Change Request contains several control accounts, each CAM can see all control accounts in the Change Details view but can only edit the control accounts for which they are the CAM. This security is based on the role in the Assigned To column of the current workflow step and works for any control account-level code listed in User Field Mapping (for example, the Manager (CAM) field). Since the process uses the user field in the data, using the Reassign feature doesn’t allow the assignee to edit data in the Change Details view. In addition to the above security setting, you cannot edit data in the Change Details view if any of the following are true:
Edit Costs in the Change Details ViewWith all change requests, you should enter changes to the schedule before editing time phased costs. This will help ensure that the work package dates are correct before you start entering costs. If the work package dates move, the time phased costs will have to be respread into the new dates which may cause a change in the cost due to rate escalation. For example, when editing a forecast that goes directly to Cobra, you should update the forecast dates in the schedule using Enter Progress before creating a Forecast Change Request and entering changes on the Cost tab. See Forecast Change Request. |
|
Control Account DatesControl account dates always exactly span the dates of all work packages within the control account. When a work package expands, because an activity date changes or because of a manual date entry, the control account start and/or finish date changes to exactly span the new work package dates. Control Account CostsEditing costs depends on the level of the change class selected in Workflow Type Configuration. If the change class is at the control account level, you can only add resource assignments at the control account level and the cost grid is disabled at the work package level. |
|
Add or Delete a Work PackageAdd a Work PackageYou can add a work package if all of the following are true:
Delete a Work PackageYou can delete a work package in the Change Details view when:
Work Package DatesWhen activities are assigned to the work package, the work package dates always exactly span the dates of all activities within the work package. When an activity start and/or finish date changes, the work package date span changes to exactly span the activity dates. Editing Work Package DatesYou can edit work package dates when:
See Respread Costs to learn how costs are respread when work package requested baseline dates are changed.Work Package CostsEditing costs depends on the level of the change class associated with the workflow type. If the change class is at the work package level, you can only add resource assignments at the work package level. You can always edit work package costs if the Create, Edit, or Delete Activities option on the Change Details on Form tab of the Workflow Type Configuration form is selected. If the Create, Edit, or Delete Activities option is not selected, you can edit the cost data at the work package level if there are no activities with resource assignments below the work package. This is because the costs are going to come from the schedule. You will be able to see the costs in the workflow steps that occur after the scheduler has applied the changes and the step action Cost Process = Integration has occurred. During data entry, Project Preferences such as Allow scope change in CA or WP do not prevent editing of data in the Change Details view. Use the integration wizard configurations to uphold settings when activity assignments are loaded from the schedule.Insert an Activity below a Work PackageYou can insert a new activity below a work package if all of the following conditions are true:
|
|
Insert an ActivityYou can insert an activity if all of the following are true:
Edit an Activity
Edit a Resource AssignmentIf the Workflow Type Configuration option Load the Change into Cost System as is set to A New or Change Amount, you will be unable to edit existing resource assignments. In order to delete a resource assignment, or reduce hours, you must insert a new line and enter a negative value to indicate a change. In order to increase hours, you must insert a new line and enter a positive value to indicate a change. Upon final approval of the change request, the difference between the two values is rolled into the final budget. For example, if a painter has 800 hours assigned and you want to reduce the hours to 600, you must insert a new line and add a painter resource assignment with an amount of -200 hours. Upon final approval, the painter resource assignment will have 600 hours rolled into the budget. If the Workflow Type Configuration option Load the Change into Cost System as is set to A New or Change Amount, you will be able to edit existing resource assignments. Delete an ActivityIf the Workflow Type Configuration option Load the Change into Cost System as is set to A New or Change Amount, you will be able to delete activities. Activity DatesActivities are at the lowest level. Their start date is based on the work package start date and their finish date is based on the work package start date plus the activity duration. If you delay the activity start date by adding a relationship or adding a constraint date, a new finish date is calculated by adding the duration to the start date. In the example below, the control account spans two work packages. Each work package spans the activities within that work package. Activity with Zero DurationWhen you add a new activity to the Change Details view grid, if you want to use the activity as a milestone, you can change the duration to zero on the General tab in the Duration field. In this case, the activity displays as an ASAP activity type with a zero duration in the Open Plan Add-In. You can change the activity type in the Open Plan Add-In if needed. |
|
Under most circumstances, you will not be able to edit data before the status date. You can never edit a forecast before the status date. You can only edit budget before the status date if the Cobra project field setting (Prevent editing of historical time phased values) indicates that you can edit historical time phased budget. |
|
Edit an EVT, or Milestone/Step
|
|
Links added to the control account, work package, or activity in the Change Details view can be viewed from the Cost Analysis and Schedule Analysis views. If a change request is canceled or deleted, the links are not deleted unless they were associated to a work package or activity that was added in the unapproved change request. These links are deleted when the change request is canceled or deleted. |