Planned Value

The budgeted cost of the work to be accomplished within a given period of time. This is usually a summary figure that incorporates multiple budgeted values, level of effort, and apportioned costs scheduled into a single figure. It is also known as the Budgeted Cost of Work Scheduled or the BCWS.