SV

Schedule Variance in dollars, hours, or equivalent persons (EQP)/heads. The difference between the budgeted cost of work scheduled and performed, expressed in dollars, hours, or EQP. Schedule variance is calculated by subtracting the Budgeted Cost of Work Scheduled (BCWS) from the Budgeted Cost of Work Performed (BCWP).