Stretching an Activity Duration
Use this procedure to stretch an activity duration.
To allow an activity duration to be stretched during resource scheduling:
-
Take one of the following actions to display the Activity Details dialog box:
- Double-click the appropriate activity.
- Right-click the appropriate activity, and click Edit Activity on the shortcut menu.
- Select the appropriate activity, and click Details in the Dialogs menu group of the Edit tab.
- On the Advanced tab, use the Max Duration field to enter the maximum time period for the activity duration if it is stretched.
- Click Apply.
Note: Open Plan stretches an activity duration only if doing so allows an activity to be scheduled that would otherwise be delayed due to insufficient resource availabilities.