Setting Up a Hammock

Use this procedure to set up a hammock.

To set up a hammocks:

  1. Create an activity and display the Activity Details dialog box.
  2. On the General tab, enter the following information for the activity:
    • Description (optional)
    • Duration: Zero
    • Type: Hammock
  3. Click the Relationships tab.
  4. Create a start-to-start relationship with the activity that represents the start of the hammock as a predecessor.
  5. Create a finish-to-finish relationship with the activity that represents the finish of the hammock as a predecessor
  6. Click Apply.