Display Resource Assignments on a Resource Histogram

Use this procedure to display resource assignments for a project.

To display resource assignments for a project:

  1. In Open Plan Explorer, select a project for which you want to display resource assignment levels.
  2. Perform time analysis on the project.
  3. In the ProjectViews folder of your project, double-click the resource histogram view.
  4. If the resource histogram view is blank, click Select Resource in the General menu group of the View tab.
    You may also right-click within the view, and click Select Resource on the shortcut menu.
  5. In the Resource Selection dialog box, select the resources for which you want to see the requirements, and click OK.
  6. In the General menu group of the View tab, click Preferences.
    If a barchart with a histogram is displayed, the option is Histogram Preferences.
  7. On the Options tab of the Histogram Preferences dialog box, select Resources, and specify the display options.
  8. Click the Resources tab.
  9. On the Resources tab, select the information you want to display, and click OK.