Use this procedure to create a resource-based schedule.
To create a resource-based schedule:
-
Perform time analysis, and evaluate the schedule.
-
If necessary, replan the project.
-
Perform time-limited or resource-limited resource scheduling, as required.
-
Display a histogram view of each resource assigned to the project to see where resources are over- or under-utilized.
-
Make adjustments to the resource usage.
You can adjust resource usage in a number of ways:
- You can select a different scheduling option.
- You can select another resource for a given activity.
- You can change the resource requirements for the activity.
- You can permit Open Plan to split, stretch, or reprofile the activity.
-
Recalculate the schedule.
-
Repeat the entire procedure as needed to develop a workable schedule.