Changing the Attached Resource File
There are two ways to change the attached resource definition file to a project.
Use any of the following methods:
- Drag-and-drop-feature
- Using the Project Properties dialog box
Warning: Deltek strongly recommends that you do not change the resource file for projects with baselines.
Related Topic
Related Procedures
- Related Topics:
- Change the Attached Resource File Using Drag and Drop
Use the drag-and-drop feature to change the attached resource file to a project. - Change the Attached Resource File Using the Project Properties Dialog Box
Use the Project Properties dialog box to change the attached resource file to a project.
Parent Topic: Related Procedures