Assigning Costs to an Activity
Use this procedure to assign costs to an activity.
To assign costs to an activity:
- Define cost resources in a resource file.
- Assign the resource file to the project.
- Select the activity to which you want to assign costs.
- On the Resources tab of the Activity Details dialog box, assign the cost resources to the activity.
- Click Apply.