Assigning Multiple Resources to Multiple Activities
Use this procedure to assign multiple resources to multiple activities.
To assign one or more resources to multiple activities:
-
In Open Plan Explorer, display one of the following views:
- Activity Barchart View
- Activity Spreadsheet View
- Network View
- Select the activities to which you want to assign resources.
- In the Dialogs menu group of the Edit tab, click Details.
- On the Resources tab of the Activity Details dialog box, select a Resource field.
- Click the ellipsis next to the input box.
- In the Select Resource dialog box, select the appropriate resources, and click OK.
- On the Assign Multiple Resources to Multiple Activities, enter the information for each of the listed resources.
- Click OK.