Use the General tab of the Resource Details dialog box to define a cost resource.
To define a cost resource:
-
In Open Plan Explorer, display a Resource View.
-
Create a resource.
-
On the General tab of the Resource Details dialog box, change the setting for the resource class to Cost.
-
In the
Unit
field, enter a measurement unit.
For some types of projects, you might set up all your costs using dollar units; for other projects, it may be more appropriate to use larger units such as millions of dollars.
-
In the
Unit Cost field, enter the base cost per unit of the resource.
-
On the Escalation tab, enter a set of escalations for the cost resource, if needed.
-
Click
Close.