Hierarchical/Subproject Procedures
- Related Topics:
- Add Multiple External Subprojects to a Master Project
Use this procedure to add multiple external subprojects to a master project through the Select dialog box. - Copy an Activity to a Subproject
Use this procedure to copy activities to a subproject. - Convert an Activity to an External Subproject
Use this procedure to convert an activity to an external subproject through the Activity Details dialog box. - Convert an Activity to an Internal Subproject
Use this procedure to convert an activity to an internal subproject through the Activity Details dialog box. - Show Summary Dates on Subprojects
Use this procedure to set Open Plan to display summary dates on subprojects through the Time Analysis dialog box. - Use External Subprojects
Use this procedure to use external subprojects in a hierarchy.