Copy an Activity to a Subproject

Use this procedure to copy activities to a subproject.

To copy activities to a subproject:

  1. Select the activity or activities you want to copy.
  2. Take one of the following actions:
    • On the Edit tab, click Copy.
    • Right-click the activity and then click Copy Activities on the context menu.
  3. Go to the appropriate subproject in the project.
  4. Take one of the following actions:
    • On the Edit tab, click Paste.
    • Right-click an empty area of the view and then click Paste on the context menu.
    The cursor shape changes to a paste tool.
  5. Click the position where you want to paste the activities.

    Open Plan automatically renumbers the copied activities, including the local portion of the ID, if necessary, to avoid duplicating existing activity IDs.