Use External Subprojects
Use this procedure to use external subprojects in a hierarchy.
To use external subprojects in a hierarchy:
- Create the project that will become the master project.
- Save the master project.
- If they do not already exist, create and save the projects that will become the external subprojects.
- In the master project, double-click an activity that will be used to represent an external subproject.
- On the Activity Details General tab, change the activity type to External Subproject.
- Click the ellipsis to the right of the External Subproject edit box.
- In the Subproject Selection dialog box, select the file to be the external subproject.
- Click OK to close the dialog box.
- When the Activity Details dialog box redisplays, click Apply.
Related Topic
Related Procedures
Parent Topic: Hierarchical/Subproject Procedures