Codes Tab of the Change Details View

The Codes tab displays labels for defined schedule, cost codes, and user fields for the selected control account, work package, or activity and allows the user to make changes to the code and user field values.

By setting up a coding system and assigning codes to your project, you can display project data at a summary level, a detailed level, or any level within the project. A good coding system provides clear and concise information. Among other things, codes are used for roll-up reporting, filtering, and processing.

See Codes Overview for additional information on codes.

When a control account or work package is selected in the Change Details grid, all codes for the selected row that have labels are displayed.

Control Account/Work Package/Activity ID

This field displays the control account ID, work package ID, and activity ID for the activity you selected in the Change Details grid.

Description

This field displays the description for the selected control account, work package, or activity.

Status

This field displays the current status for the selected activity: Planned, In-Progress, or Complete.

Codes Grid

Grid Toolbar

Option

Description

Codes

Click the drop-down arrow to display the following options:

  • Print — Select this option to display the Print Preview form.

  • Export to Excel — Select this option to open the Microsoft Excel application with the grid’s contents displayed.

Grid Columns

Field Name

Description

Description

This column displays the cost and schedule code labels.

Value

This column displays the code value for the selected control account, work package, or activity.

Click to display the Code Search dialog box.

Use Code Search to select the code for activities of the selected project or add codes to a work package level. The content of this search dialog depends on the code file available in your cost or scheduling system.

For Text, you can manually edit the Value using the text field.

User Fields Grid

This grid displays the user fields defined on the Source Fields tab of the User-Defined Data form under the cost and schedule area.

When a control account, work package, or activity is selected in the Change Details grid, the cost and schedule user-defined fields (character, date, and numeric fields) for the selected row are displayed.

Grid Toolbar

Option

Description

User Fields

Click the drop-down arrow to display the following options:

  • Print — Select this option to display the Print Preview form.

  • Export to Excel — Select this option to open the Microsoft Excel application with the grid’s contents displayed.

Grid Columns

Field Name

Description

Description

This column displays the cost and schedule user-defined field labels.

Value

This column displays the field value for the selected control account, work package, or activity.

What do you want to do?

Define cost code labels

Define schedule code labels

Enter a code assignment on an activity

Add a source field to the workflow table

Define fields in Open Plan