External Relationships

This topic includes the following topics relating to external relationships:

Relationships in Different Projects within the Same Master Project

Open Plan supports master projects with external subprojects and it is not uncommon to have relationships between external subprojects. After you add the Open Plan master project on the Project Schedule Integration tab, you can create relationships to subprojects within the same master project.

All of the projects involved in the change request must belong to the same Open Plan master project and none of the subprojects can have external subprojects. Before you get to the Apply or Approve Change Open Plan Add-In step in the workflow, all of the master project subprojects must be time analyzed and the results saved to the database.

When the Scheduler approves the change request in the Open Plan Add-In, PM Compass simulates the external relationships by adding a milestone activity for each relationship that you added in the Change Details view.

Note:

External Activity Attributes

During the Add-In step, since the master project is not opened, the external relationships are simulated by creating milestones with relationships. The attributes of the milestones are listed below.

When the external activity is a predecessor, the newly added milestone has the following attributes:

When the external activity is a successor, the newly added milestone has the following attributes:

Adding and Viewing External Relationships As Part of a Change Request

These steps outline what is required to support adding external relationships.

Step

Description

Add a Master Project

In order to add a relationship to an activity from another project, you must first add the master project on the Schedule Integration tab.

Add an External Relationship in a change request

After adding a master project to the Project Schedule Integration tab, you can add external relationships using the Predecessor/Successor Search dialog box that you can access on the Change Details Relationships tab. The External Subproject field on this dialog box lists all of the Open Plan projects within the master project, except for the project selected on the Projects form. After you have selected an external subproject, the activity list in the dialog box displays all activities (<project>.<activity ID>) in that project.

While you can add external successor relationships, Deltek recommends that you add successor relationships in a workflow with the successor activity project. Using this process, the effects of the external relationship can be analyzed and the baseline of the successor activities can be updated.

You cannot add external relationships while in the Add-In step.

Use the View Summary Grid

When you add an external relationship to a change request, the relationship is added to the View Summary grid in the External Predecessor or External Successor column and displays as <Project Name>.<Activity ID>.

Confirm the Relationship

After you complete the workflow, you can confirm the relationship in Open Plan in one of two ways:

  • Open the master project to see the interconnecting link between the subprojects. You cannot open the Master Project while you are in the Apply change or Approve Change Open Plan Add-In steps in the workflow.

  • Open the subproject that you selected in the PM Compass workflow. The external activity displays in gray. External relationships are not visible in the external subprojects until the workflow is completed.

Relationships within the Same Project but External to the Selected Control Account

You can add (or edit) a relationship to an activity that is not linked to the control accounts selected on the workflow form.

Creating Relationships

On the Change Details View Relationships tab, when you click Insert, and then click the lookup icon () in the Predecessor or Successor cell, by default, the Predecessor/Successor Search dialog box only displays the activities linked to the control account on the workflow form. To see all activities in the project, select the Show All Activities option on the Predecessor/Successor Search dialog box.

The Predecessor / Successor Search dialog box also includes an External Subproject field that is available after you add an Open Plan master project on the Project Schedule Integration tab. It lists all of the Open Plan projects within the master project, except for the project selected on the Projects form. Select the external subproject that includes the activity for which you want to add the relationship. After you select the external subproject, the external subproject activities display in the grid. After you select an activity and click Select, the Activity ID column in the Change Details grid displays <project>.<activity ID>.