Enter Planned Hours and Amounts
Use the grids on the Labor, Expenses, Consultants, and Units tabs of the Plan form to enter planned hours, amounts, and quantities.
- Related Topics:
- Enter Summary Planned Hours in Project Planning
To have Vantagepoint allocate summary planned hours to individual resource assignments for a project on the Labor tab of the Plan form in the Projects hub, select the project and enter the summary hours in the ETC Hours field at the appropriate level of the plan work breakdown structure (WBS). - Enter Planned Hours in Calendar Period Columns in Project Planning
To enter planned hours for resources for specific calendar periods (days, weeks, or months) on the Labor tab of the Plan form in the Projects hub, select the project, expand the plan work breakdown structure (WBS) to display the WBS elements or resources for which you want to enter hours, and enter the hours in the appropriate calendar period fields. - Enter Summary Planned Amounts for Expenses
If you enabled planning for expenses, you can enter planned amounts for them on the Expenses tab of the Plan form in the Projects hub. - Enter Contract Compensation Amounts for Units
On the Contract tab of the Plan form, use the unit contract columns to specify which portion of a compensation amount is used for units. - Enter Planned Quantities for Units
On the Units tab of the Plan form, expand the work breakdown structure (WBS) to display the unit assignments for which you want to enter quantities. You cannot enter quantities for WBS elements.