Fields and Options
Use the Project View toolbar options and grid, and the related dialog boxes, to review resource assignments for a selected project, add new assignments and enter planned hours, and make changes to existing assignments.
- Related Topics:
- Project View Form
Use the Project View form to review resource assignments and schedules for your projects, assign employees and generic resources to your projects, and enter planned hours for those assignments. You can also use the form to reassign work from one resource to another and to reschedule planned hours - Grid Settings Dialog Box for Project View
Use the Grid Settings dialog box to select a sorting option for resources in the Project View grid and to select columns to display in the middle section of the grid. - Assign Resources to Project Dialog Box
Use the Assign Resources to Project dialog box to assign resources to work on the project that you selected in the Projects hub or in Project View in Resource Management. - Change Scale Dialog Box
In Project View, and on the Plan form in the Projects hub, you can view and enter plan data using different time scales, for example, by weeks or by months. Use the Change Scale dialog box to switch from one of these scales to another. The calendar period column headings change to reflect your selection, and any existing hours or amounts in those columns are recalculated based on the new scale. - Reschedule Dialog Box
To change plan dates or assignment dates for plan rows, use the Reschedule dialog box to enter the new dates and to indicate how you want the schedule change to affect the distribution of planned labor hours. - Reassign Dialog Box
If you assign work on a project to an employee or generic resource and later want to transfer all or part of the assignment hours to another resource (for example, from a generic resource to a new employee you have just hired for the project), use the Reassign dialog box to indicate if you want to reassign all or only part of the hours and to select the resource to which you want to reassign them. - Check In Plans Dialog Box
Use the Check In Plans dialog box to check in project plans manually. The dialog box displays all plans that are currently checked out to you and to others.
Parent Topic: Project View