Type
|
For a consultant resource, select from your list of consultant vendor types.
For an expense resource, select from your list of expense activities.
|
Resource
|
Enter the consultant vendor or expense. Required for commitments.
|
Reference/Commitment #
|
Enter an ID that you want
to assign to this consultant or expense budget item.
Always enter an ID in this field.
|
Cost
|
Enter the amount that you expect to pay the vendor for the committed work.
|
Contract
|
Enter this amount or change it, if needed. It is the amount that you
expect to bill the client. Ajera calculates it for you by multiplying
the cost amount by any markups from the applicable rate table. Required
for commitments.
Note: |
You can
reset all amounts for the entire project back to the amounts Ajera calculated
for you by clicking the icon. |
|
Committed cost invoiced
|
unavailable in ajeraCore unless you have the Consultant Management add-on
If you have not yet selected the Project beginning balances complete check box on the Project tab of Company Preferences, enter the cost amount already invoiced from the vendor against this budget item.
If this column is not visible on the Manage tab, see Adding the Committed columns to the Manage tab.
|
Committed contract invoiced
|
unavailable in ajeraCore unless you have the Consultant Management add-on
If you have not yet selected the Project beginning balances complete check box on the Project tab of Company Preferences, enter the contract amount you have already invoiced to the client for this budget item.
If this column is not visible on the Manage tab, see Adding the Committed columns to the Manage tab.
|
Notes
|
Enter any notes for this budget item.
|