Advanced Tab
The Advanced tab allows you to set advanced controls. You can also perform resource scheduling without displaying this dialog box by clicking Resources in the Schedule menu group of the Processes tab.
You can perform resource scheduling in Batch Mode. This allows you to run resource scheduling for multiple projects at one time. To run resource scheduling in Batch Mode, select more than one project from the Details pane of the Open Plan Explorer, and click the Resource Scheduling button. The Resource Scheduling[Batch Mode] dialog box will be displayed. Set your options, and click OK.
If a project is closed, Open Plan will open it in Exclusive mode, perform the process, save the changes, and then close the project. If a project cannot be opened in Exclusive mode (because another user has it open in Exclusive or Shared mode), it will be skipped.
If you have a project open when the batch process is run, resource scheduling will be performed on the project, but the changes will not be saved and the project will remain open. You must manually save the changes yourself.
Open Plan creates one resource scheduling session log, listing the project results in the order in which the projects were processed in the batch.
Related Topics
Related Procedures
- Related Topics:
- Contents of the Advanced Tab of the Resource Scheduling Dialog Box
Use the fields and options to configure the Advanced tab of the Resource Scheduling dialog box.