Entering Resource Progress Information
To enter resource progress information in Open Plan, use the Resources tab of the Activity Progress dialog box.
You can display this dialog box by selecting an activity and clicking Progress on the Edit tab in any activity view or by right-clicking the row button of an activity and clicking Progress on the context menu.
If you scroll through the fields displayed in this dialog, you can see the current actual costs and usage for each resource as well as the budgeted costs and units for all assigned resources. Budgeted costs of resources reflect any cost escalations defined for the resource based on the period of the original assignment.