Activity Progress
In general, entering status information about activity progress consists of specifying the related information so that a revised time analysis of the project can be performed.
The information includes:
- Has the activity started? If so, when?
- Has the activity ended? If so, when?
- If
the activity has started but not yet ended, how long is the remaining duration?
It is important to make sure that all progress information up to Time Now has been entered. The Time Now date (sometimes referred to as the status date) refers to the date for which all the progress data in a project has been reported. Open Plan assumes that no future work for the project (including activities which have not yet started and activities which have been started but not completed) can be scheduled prior to the Time Now date. For example, a Time Now of 01Jun15 means that all progress data in the project up to and including 31May15 has been reported, and that Open Plan does not schedule any work for the project prior to 01Jun15.
It is recommended that you enter actual dates for progressed activities whenever possible. If you omit an actual start or actual finish date when entering project progress, Open Plan deduces the dates for the purposes of internal calculations based on the status code entered and Time Now.
- Related Topics:
- Entering Activity Progress
There are several ways to enter activity progress. - The Effect of Activity Progress Information
Once you have entered progress for activities, you can calculate new early start/finish and late start/finish dates using time analysis and new scheduled start/finish dates using resource scheduling. - New Activities
Before progressing a new activity, you should run time analysis otherwise the resource assignment physical percent complete may not be updated.