Use this procedure link activities in Open Plan.
If relationships already exist between the selected activities, Open Plan would not allow you to modify the existing relationships.
Note: You can also use the Add Relationship dialog box to define relationship between activities.
-
In Open Plan Explorer, open an activity spreadsheet, a resource or an activity barchart, or a network view.
-
Select the activities or tasks to which you want to add relationships.
-
Take one of the following actions to display the Link/Unlink Activities dialog box:
- From the Edit tab, of the activity spreadsheet, resource or activity barchart, or network views, select
Link/Unlink Activities. This option only becomes enabled when you select two or more activities.
- From the context menu of an Activity spreadsheet, a resource or an activity barchart, or a network view, select
Link/Unlink Activities.
When you use
Ctrl + Click to select and link activities, Open Plan links the activities in the order in which you selected them.
-
Select or enter necessary information.
-
Click
Link.
Open Plan then creates the relationship between the selected activities using the relationship type, lag, and calendar that you specified on the dialog box.
Note: Open Plan displays all errors that occur when linking activities on the Link/Unlink Activities Errors dialog box after the process completes.