Import MRP Estimate to Complete (ETC) Baseline Data
This procedure allows you to import MRP ETC resource data into the Open Plan ETC Baseline, replacing existing baseline resource data for all activities included in the import.
The MRP data you are importing should match the data in the Open Plan project. Otherwise, an error message displays and the import process stops.
Note: You can only perform the MRP ETC Baseline Import process when there is an active single project opened in
Exclusive mode and there are available baselines on the project. In addition, there should only be one instance of Open Plan running on the same machine.
To import MRP ETC Baseline Data:
Related Topics
Parent Topic: Related Procedures